Issaquah Transit Center / SR 900 Main Site -
Sound Transit
Work continues on the Issaquah Transit Center. Shoring and formwork are complete
for the fourth (and final) level elevated deck, placement of structural concrete and post tensioning is
complete for levels one through three and underway for level 4. The Transit Island foundation has been
placed. The storm water detention vault is complete. Transit Island steel erection is underway. Barrier
cables and structural steel erection on the main structure is underway.
|
| 