HomeAbout UsPortfoliioNews & EventsCurrent ProjectsOn-line ProjectsContact Me
 
 
Carnation Wastewater Treatment Facility
King County Department of Natural Resources

Work continues on the new Carnation Wastewater Treatment Facility for King County. Structural concrete, underground piping, effluent stand pipe, conveyance pipeline, operations building and the main structures are now complete. Mechanical, process piping and electrical work is underway.
 

 
Operations Bldg and Headworks Structure
Operations Bldg and Headworks Structure
  Aerial View of Aeration Basins
Aerial View of Aeration Basins
 
Effluent Standpipe and Chemical Storage
Effluent Standpipe and Chemical Storage
  Aerial View of MBR Tanks
Aerial View of MBR Tanks
 

 
Issaquah Transit Center /
SR 900 Main Site - Sound Transit

Work continues on the Issaquah Transit Center. Shoring and formwork are complete for the fourth (and final) level elevated deck, placement of structural concrete and post tensioning is complete for levels one through three and underway for level 4. The Transit Island foundation has been placed. The storm water detention vault is complete. Transit Island steel erection is underway. Barrier cables and structural steel erection on the main structure is underway.
 

Installation of the shoring and formwork for Level 4
Installation of the shoring and formwork for Level 4
 
Parking Structure
Parking Structure
  Parking Structure
Parking Structure
 

 
SeaTac Airport Industrial Wastewater Treatment Lagoon No. 3 Pump Station Improvements - Port of Seattle

Harbor Pacific Contractors has completed installation of the new 45' deep 144" diameter wet well for the Port of Seattle's Industrial Wastewater Treatment Plant Lagoon 3 Pump Station. The new Headworks influent screen is now installed and the 20" diameter forcemain is complete. Harbor Pacific Contractors met the Port's completion milestone of October 15, 2007 for operation of the pump station and influent screen.
 

 
Drilling shaft for new 12' diameter wet well
Drilling shaft for new 12' diameter wet well
  New 45' deep wet well
New 45' deep wet well
 

 
SeaTac Airport Third Runway Project Lighting Vault - Port of Seattle

Work is underway to construct a new lighting vault (building) as part of the Port of Seattle's new third runway expansion. Harbor Pacific Contractors has completed the foundation slab, transformer and rectifier foundations, the exterior masonry walls and the steel framed roof system of the building.
 

Preparation for concrete base slab
Preparation for concrete base slab
 
Placement of concrete for base slab
Placement of concrete for base slab
  Masonry walls for new structure
Masonry walls for new structure
 

 
 
Harbor Pacific Contractors, Inc.